Near North Central area ADA pedestrian ramp upgrades and resurfacing
Dates
2023 - 2024
Location
Area bounded by Knox Ave North, Plymouth Ave N, Aldrich Ave N, 15th Ave N., and 16th Ave N Near-NorthProject overview
This project is part of the ongoing street maintenance program
ADA pedestrian ramp upgrades
The City upgraded pedestrian ramps to current Americans with Disabilities (ADA) standards. This work was completed in 2023.
Resurfacing
City staff resurfaced the streets in this area in 2024. We replaced the top layer of asphalt pavement to extend the life of a street. The new pavement should last at least 10 years.
View the Near North Central area ADA Pedestrian Ramp Upgrades and Resurfacing Documents
Schedule
Project schedule:
- Mill and overlay work to begin the week of July 22, 2024.
- Select curb and gutter replacement work began the week of June 3, 2024.
Traffic impacts
The road will be closed to traffic in intervals during milling and paving for periods of time. Roads will remain open during the evenings and nights.
Project phase
This project is in progress.
Input
Design
In Progress
Complete