West Fulton Neighborhood Improvement
Dates
2025 to 2031
Location
Neighborhood streets in the area extending from France Ave S to Xerxes Ave S, and from 47th St W to 54th St W. FultonProject overview
The City is planning to make improvements to neighborhood streets in the Fulton neighborhood. The project area extends from France Ave to Xerxes Ave and from 47th St to 54th St. Some streets will be resurfaced and others will be reconstructed. The work began in 2025 and will continue over the next several years.
The project will:
- Repair or replace deteriorating pavement
- Install rain gardens to help filter stormwater
- Implement bike network upgrades
- Improve pedestrian curb ramps
- Incorporate traffic calming designs
- Improve underground storm sewer pipes within the right of way where needed
Residential street resurfacing
Fall 2026
Improvement type
Residential Street Resurfacing
Special assessments
Yes
Project length
3.9 miles
Resurfacing team contact
If there are any questions about street resurfacing, contact
Community engagement events
Staff held a special assessment and project information meeting on June 17, 2025 at the Pershing Recreation Center.
Rain garden installation
Summer 2026
Improvement type
Rain garden installation
Project area and schedule
Rain garden construction is anticipated to begin mid-August, 2026. Rain gardens will be built in two phases.
Rain garden team contact
If there are any questions about the rain garden installation, contact
Full depth reclamation
Fall 2026
A full depth reclamation (FDR) rebuilds more of the street than a resurfacing project. The existing pavement and base materials are ground up, mixed together, and compacted. Then, a new layer of pavement is added on top. This process can fix deeper pavement problems that resurfacing cannot.
Read more about FDR and other types of repair
Improvement type
Full depth reclamation
Special assessments
Yes
Project length
2 blocks
Project area
- Chowen Ave S from W 51st St to W 52nd St
- Beard Ave S from W 51st St to W 52nd St
Full depth reclamation team contact
If there are any questions about the full depth reclamation, contact
Ryan Gottsleben - Project Engineer
Community engagement events
Staff held a virtual special assessment and project information meeting on June 9th, 2026.
Community engagement
Office hours
Project staff hosted office hours in-person and virtually to answer any questions from residents on February 25 and 26, 2026.
Open house phase 2
The project team held an open house on April 22, 2025.
Open house phase 1
The project team held a virtual open house on October 7, 2024. This open house provided an introduction and overview of the project.
Project schedule
Refer to the project overview for the most up-to-date phasing information.
View the W Fulton project overview
Rain garden installation
Full depth reclamation
Residential resurfacing
West Fulton neighborhood improvements
Public Works special assessments links
Special assessments
Learn about the assessment fees and the assessment process
Assessment lookup
Approved special assessments in pending or levied status can be viewed through our eProperty portal.
Project resources
Project phase
This project is in progress.
Input
Design
In Progress
Complete
Sign up for project updates
Sign up to get alerts about this project. You'll need to provide your email address.